    Every BC custom home needs a service size: 100, 200 or 400 amps, with a load calculation that the electrician files with BC Hydro. Add a heat pump, a tankless water heater, an induction cooktop, an EV charger and a secondary suite and the easy 200-amp service is no longer easy. Here is how we size the panel on a new build, what the Canadian Electrical Code asks for, and where 400 amps earns its place in Burnaby.

    Every BC custom home needs a service size, decided at concept, not at the panel. The service is the connection from the utility to the house, measured in amps at 240 volts. The three common choices are 100, 200 and 400 amps. The number is fixed by the Canadian Electrical Code load calculation and by what the house is going to run.

    This post covers how we size the electrical service on a Burnaby custom home, what the Canadian Electrical Code (CSA C22.1) asks for, and when 400 amps earns its place over 200. Our post on electrical planning covers the panel layout, and this one covers the size.

    What a service size actually means

    A service size is the maximum sustained current the utility will supply to the house, in amperes, at a nominal 240 volts. The service passes through:

    • The service drop or lateral, from the pole or the underground pad to the house.
    • The meter base on the outside of the house.
    • The main breaker in the panel.
    • The panelboard, which splits the service into the branch circuits.

    Every one of those parts is sized to the service amp rating. Going from 200 amps to 400 amps changes the service conductor size, the meter base, the main breaker, the panelboard, and in some cases the utility transformer. It is cheap at framing and expensive after.

    The code load calculation

    CSA C22.1 Section 8 sets the method for calculating the minimum service size. The electrician totals the loads in the house with specified demand factors and reads the required amps from the result. The calculation covers:

    • The basic load, based on the floor area of the house, with a demand factor.
    • Electric heating (a heat pump, a backup electric resistance strip, a baseboard, radiant floor heating), with demand factors.
    • Electric water heating, whether tankless or storage.
    • The range or cooktop and wall ovens, with demand factors.
    • Electric clothes dryers.
    • Air conditioning, where separate from the heat pump.
    • Electric vehicle chargers, at their rated current.
    • Any additional load over 1,500 watts per Section 8.

    The number that comes out is the minimum service. We always design to the real life load, which is usually a little higher.

    The electrification pressure in BC

    Three changes in BC are pushing more houses from 200 amps to 400 amps:

    • Heat pumps replacing gas furnaces and gas hot water. The BC Energy Step Code at Step 4 and Step 5 is close to all-electric. The 2024 Zero Carbon Step Code pushes further. Our post on the Zero Carbon Step Code covers the rule.
    • Induction replacing gas cooktops. A 30-inch induction cooktop pulls up to 40 amps on peak. Our post on induction vs gas cooktops covers the swap.
    • EV charging in the garage. A Level 2 charger draws 32 to 48 amps when the car is plugged in. Two EV chargers and the demand climbs.

    Line up a heat pump, a heat-pump water heater, an induction cooktop, two EV chargers and a hot tub, and a 200-amp service is at its ceiling or past it.

    When a 200-amp service is enough

    A well-designed 200-amp service covers most Burnaby custom homes:

    • A single detached house with a reasonable heat pump sized to the house.
    • A heat-pump or tankless water heater.
    • An induction cooktop and double wall ovens, or a gas range.
    • A single Level 2 EV charger.
    • Standard appliances.
    • No secondary suite running at full load at the same time.

    The load calculation checks out for that profile at 200 amps. The electrician builds the panel with headroom, usually 20 to 30% of breaker space free for future circuits.

    When 400 amps earns its place

    A 400-amp service earns its place when the load calculation crosses the 200-amp ceiling. Common cases on a Burnaby custom home:

    • A heat pump plus a secondary suite with its own heat pump, water heater, cooking and EV charging. The code lets a single service supply both dwellings, with subpanels each with their own disconnect. Our post on secondary suites covers the rules.
    • A large house with two or more EV chargers at the real rated current.
    • A workshop subpanel in a detached garage, with welding, wood machines or a small CNC. Our post on garage workshops covers the space.
    • A hot tub, a sauna, a steam shower and radiant floor heating on top of the base loads. Our posts on steam showers and home spas and radiant vs forced-air heating cover those systems.
    • Snow melt on a driveway, which is an electric load in the tens of kilowatts.
    • Pool equipment and a pool house, where the pool subpanel adds a second large zone.
    • A large PV solar array with a battery system, where the service has to take back-feed from the inverter.

    For any of those, the electrician runs the calculation and often lands on 400 amps.

    Load management: the middle path

    The Canadian Electrical Code allows a load management device to limit a controllable load (usually an EV charger or a hot tub) when the rest of the house is at its peak. The device watches the main service current and, when the total approaches the service limit, it dials back the EV charger. The car charges slower for a while, then returns to full speed when the house settles down.

    Load management can keep a house inside a 200-amp service that would otherwise need 400 amps:

    • A two-EV-charger setup managed to a shared 40-amp budget.
    • A hot tub on a load-managed circuit that drops to idle when the induction cooktop is in use.
    • An EV charger managed to the whole-house peak, not its own budget.

    Two conditions:

    1. The utility and the authority having jurisdiction accept it. BC Hydro and the local electrical inspector do.
    2. The device is listed, and the electrician includes it in the load calculation on file.

    For an owner who wants to electrify fully but keep the 200-amp service, load management is often the right answer. For an owner with a workshop, a suite and a large house, 400 amps is often simpler.

    Heat pump, induction, tankless water heater and one EV charger fit in 200 amps. Add a suite, a second charger and a hot tub, and 400 amps is the right answer.

    Icon Projects Team

    The physical service: what changes at 400 amps

    Going from 200 to 400 amps changes:

    • The service conductor size. The feeder from the utility to the meter base is larger.
    • The meter base. 400-amp meter bases are physically larger and more expensive.
    • The main disconnect. Some 400-amp services use a single main breaker. Others use two 200-amp mains in parallel panels, which is a common and code-compliant layout in BC.
    • The panelboard. More breaker positions, more branch circuits, more wall space. Our post on electrical planning covers the panel layout.
    • The service conduit and the trench, for an underground service.
    • Occasionally the utility transformer. BC Hydro reviews the service application and may upgrade the pole-top or pad transformer feeding the house.

    Where the panel goes

    The main panel sits in an accessible location in the house. Common choices:

    • The mechanical room, usually in the basement or on the main floor. Our post on mechanical room planning covers the room.
    • The garage, on an interior wall (not the car-facing wall, where a car bumper could hit it).
    • A utility closet on a single-storey house without a basement.

    The code requires a working space in front of the panel, kept clear: at least 1 metre deep, 750 millimetres wide, and a 2-metre headroom. The panel location is agreed at framing, not at electrical rough-in, because the service conductor path and the clear zone shape the plan.

    What a suite changes

    Burnaby allows secondary suites in most R1 lots. A suite adds its own loads:

    • A small heat pump or baseboard heater.
    • A water heater.
    • A range or cooktop.
    • A clothes washer and dryer.
    • Standard lighting and receptacles.

    Two ways to serve the suite:

    • A single service with two subpanels, each with its own disconnect and billing meter. The electrician files the load calculation for both dwellings together. This is the most common layout in Burnaby.
    • Two separate services, one per dwelling. Rare on a shared house.

    Our post on secondary suites in a Burnaby custom home covers the zoning and code rules, and suite plumbing covers the plumbing side.

    Rough-ins and future headroom

    Even on a 200-amp service, we leave physical headroom in the design:

    • Empty conduit from the panel to the garage for a second EV charger.
    • A spare conduit to the mechanical room, for a future battery system or heat-pump upgrade.
    • Reserved breaker space in the panel, usually 20 to 30 percent of the slots, with the end-of-panel space free for a second main-lug if the service is later upgraded.
    • A wall big enough beside the panel for a future subpanel, if the house is set up for a suite at a later date.

    The rough-ins are inexpensive at framing and expensive to retrofit. Our post on EV charger rough-in covers the car side.

    How we size the service on a Burnaby build

    1. Build the appliance and equipment list at design, including heating, water heating, cooking, EV charging, outdoor loads and suite loads.
    2. Run the Canadian Electrical Code load calculation with the electrician, using the real appliances, not a generic template.
    3. Pick the service size at the result, with a margin for the real-life peak.
    4. Consider load management where it keeps a 200-amp service viable and saves the owner the cost of a 400-amp upgrade.
    5. Choose the panel location and confirm the service path with BC Hydro and the electrical inspector.
    6. Leave rough-ins for the EV charger expansion, the suite, the battery system and the workshop.
    7. File the service application with BC Hydro, with the load calculation attached.

    Our custom homes service page shows how we build in Burnaby, Coquitlam and across the Lower Mainland.

    Frequently asked questions

    What is the difference between a 200-amp and a 400-amp service?
    The service size is the maximum current the utility supplies to the house at 240 volts. A 200-amp service can carry about 48 kilowatts of continuous load. A 400-amp service is double that. The difference affects the size of the service conductor, the meter base, the main breaker and the panelboard, and in some cases the transformer the utility connects to.
    Can a 200-amp service run a heat pump, induction, tankless water heater and an EV charger?
    Sometimes. A well-designed 200-amp house with a modest-sized heat pump, an induction cooktop, a heat-pump water heater, one Level 2 EV charger and standard appliances meets the Canadian Electrical Code load calculation. Add a second EV charger, a hot tub, a workshop subpanel and a secondary suite, and the load calculation forces 400 amps.
    What is a Canadian Electrical Code load calculation?
    CSA C22.1 Section 8 sets a formula that totals the connected loads in the house with demand factors, and gives the minimum service size the house needs. The electrician does the calculation with the appliance schedule, the heating system, the EV charging plan and any suites. The utility reviews the calculation when the service is applied for.
    Where does the panel go in a custom home?
    The main panel sits in an accessible location, usually a mechanical room, a garage or a utility closet. The Canadian Electrical Code requires a working space in front of the panel (at least 1 metre deep, 750 millimetres wide, 2 metres high) kept clear. We also keep it close to the service entrance to shorten the heavy service conductor run.
    What is a load management device and can it reduce the service size?
    A load management device dynamically limits the current to a large load (usually an EV charger or a hot tub) when the house is at its peak, so the total never exceeds the service capacity. The Canadian Electrical Code allows it to be used in the load calculation, which can keep a house inside a 200-amp service that would otherwise need 400 amps. The utility and the authority having jurisdiction have to approve the device.
    Do we need separate services for a secondary suite?
    The code allows a single service for the whole house with separate subpanels for each dwelling unit, each with its own disconnect and metering. The utility decides whether to meter the suite separately for billing. In Burnaby, where secondary suites are allowed in most R1 lots, we usually fit a subpanel for the suite in its mechanical area and leave the service as one. Our post on secondary suites covers the rules.

    Free Field Guide · 9 pages

    Before You Break Ground: The Vetting Checklist for Hiring a Custom Home Builder in BC

    The 30 questions we'd want a homeowner to ask any builder, including us, before signing a contract. We'll email you the PDF.

    • How to verify a BC Housing licence and 2-5-10 warranty
    • What 'good' looks like for site supervision and change orders
    • Five walk-away signs that should end any builder conversation

    We'll email you the download link. No newsletter, we won't share your email or send you anything you didn't ask for.

    Or follow the daily build on Instagram, site visits, finish details, time-lapses from current Icon projects.

    Follow @iconprojectsltd

    Build with Icon

    Have a project in mind?

    A short conversation is the fastest way to understand whether Icon is the right partner for what you're planning.

    Book Your Services