Custom Home Guide · Chapter 2 of 6

    Design & Drawings

    What you pay for in design isn't lines on paper, it's decisions you won't have to remake on site at five times the cost.

    Architect vs. builder drawings

    A licensed architect is required in BC for some scopes and optional for most single-family work. Architect-led drawing sets are typically more rigorous on form, light and structural concept; builder-led sets (with a designer and coordinating engineers) are usually more buildable and faster to permit. Neither is universally correct, the question is which the lot, the program and the municipality reward.

    The Architectural Institute of BC publishes the scope-of-practice rules. Read them before assuming you do or don't need an architect.

    Permit-ready isn't the same as construction-ready

    A drawing set that passes permit review still has to be developed into a working construction set, shop drawings, full envelope details, mechanical coordination, structural connections. If your design contract ends at permit, you'll be paying twice for the gap. Pre-construction services agreements exist to bridge it properly.

    Decision-stacking is the silent budget killer

    Most cost overruns aren't caused by one big change, they're the cumulative weight of fifty deferred decisions. Bringing material, mechanical and finishing questions forward into the design phase, when changes cost a redline instead of a re-pour, is the single biggest predictor of a build that lands on time.

    When this chapter applies

    A quick framing of when the advice above is the right advice, and when it isn't.

    Best for

    • Owners committing to a fully custom program who want one source of truth.
    • Hillside, heritage or unusual lots that warrant architect involvement.
    • Anyone whose builder is in conversation before drawings are finalised.

    Fails when

    • Drawings are commissioned in isolation and handed to a builder afterward.
    • Design firm is not coordinating with the structural and mechanical engineers.
    • Owner keeps making finish-level decisions after the permit is submitted.

    Verify before acting

    • Confirm the design contract covers post-permit construction documents.
    • Confirm AIBC registration and current licence for any named architect.
    • Confirm coordinating engineer scope (structural, mechanical, envelope).

    Go deeper in the Journal

    Detail-level posts that expand on specific topics from this chapter.

    Official sources

    Ready to Start

    Talk to a builder who's done this 100+ times.

    If you're partway through this guide and the questions are getting specific, that's the right moment to bring us in. Planning calls are free.